Title: PROPOSED COST ESTIMATES FOR THE MARGATE BOULEVARD IMPROVEMENTS PROJECT
Attachments: 1. BACKGROUND: EOPCC, 2. BACKGROUND: TASK ORDER NO. 1, 3. BACKGROUND: TASK ORDER NO. 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

 

TO:                     Margate CRA Chair and Members of the Board

 

FROM:                     Cale Curtis, CRA Executive Director

 

DATE:                     May 10, 2023

 

 

Title

PROPOSED COST ESTIMATES FOR THE MARGATE BOULEVARD IMPROVEMENTS PROJECT

 

Body

 

 

BACKGROUND:                      On February 16, 2023, Chen Moore and Associates, Inc. (CMA) presented the Board with several design options as part of the development of additional design considerations under approved Task Order No. 2.  In order to address constructability and understand the value of CMA’s preferred improvements to the corridor, the Board requested comparable construction costs.  This would allow for a better understanding of the impact CMA’s design preferences may have on the overall construction cost.

 

On August 17, 2022, the Board authorized the approval of Margate Blvd Improvements Project Task Order No. 2 to CMA for additional civil engineering, landscaping, and construction administration services. The additional services include the engineering design for improvements, such as, additional demolition and construction of sidewalks, considerations for the type of delineation for parallel parking, and adjustments to landscaping preferences along the right of way of Margate Blvd from SR7/US 441 to East River Drive and portions of NW 58th Avenue from Park Dr. to approximately the alleyway north of the Margate Blvd roundabout.

                     

Proposed improvements under the original approved Task Order No. 1 included, but was not limited to: providing professional civil engineering, planning and landscape architecture services for the design (including improvements designed to address sidewalk and crosswalk issues and to meet current ADA standards, as well as to address inconsistent landscape designs and plantings); permitting; and construction administration services necessary for completion of the project. The originally approved Task Order No. 1 with Purchase Order (PO) in the amount of $94,166.00, was issued in July 2021.  The cost of approved Task Order No. 2 with PO, in the amount of $66,975.00, was issued in November 2022.

                     

The purpose of this agenda item is to obtain the Board’s guidance and input after consideration of the type and potential cost of proposed improvements envisioned for Margate Blvd. CMA will be presenting this item to the Board. Following the Board’s feedback, the Bid and Build (construction) phases are expected to follow.  These phases will be brought back to the Board for review and/or approval, as applicable.

 

 

RECOMMENDATION:                     Provide feedback to staff related to preferred design options that would be incorporated into the Design Plans for Margate Boulevard Crosswalk and Landscape Improvements.

 

 

FISCAL IMPACT:                     To date: approximately $161,141.00 for Design ($66,975.00 for current Task Order No.2. and $94,166.00 for original Task Order). The project is being funded under the approved Margate Boulevard Improvements budget line of the Capital Improvements Program Fund; account number: 340-0510-512.69.17.    

 

 

 