TO: Margate CRA Chair and Members of the Board
FROM: Cale Curtis, CRA Executive Director
DATE: November 10, 2026
Title
AUTHORIZING THE APPROVAL OF TASK ORDER NO. 4 WITH CHEN MOORE AND ASSOCIATES, INC. FOR ADDITIONAL CIVIL ENGINEERING, LANDSCAPING AND CONSTRUCTION ADMINISTRATION SERVICES FOR THE MARGATE BOULEVARD CROSSWALK AND LANDSCAPE IMPROVEMENTS PROJECT
BACKGROUND: On July 13, 2021 the Board approved Task Order No. 1 with Chen Moore and Associates, Inc. (CMA). Project tasks included but were not limited to providing professional civil engineering, planning and landscape architecture services for the design, permitting and construction administration services (including an initial 10 site visits) necessary for the completion of the project. These included improvements designed to address sidewalk and crosswalk issues and to meet current ADA standards, as well as address inconsistent landscape designs and plantings.
Task Order No. 2 to CMA was approved by the Board on August 17, 2022 for additional civil engineering, landscaping, and construction administration services (which included an additional 16 site visits). The additional services included design engineering services to replace all paver sidewalks, parallel parking, and adjustments to landscaping preferences along the right of way to Margate Boulevard from SR7/US 441 to East River Drive and portions of N.W. 58th Avenue.
In May of 2025 the Board approved an agreement with FG Construction and construction commenced on August 14, 2025. In December 2025, Task Order No. 3 to CMA was approved by the Board to provide additional inspection associated services during construction which included an additional 110 site visits, responding to requests for information, pay application reviews, change order reviews, conducting construction inspections and progress meetings. At that time, the anticipated contractual completion date was April 11, 2026. The extended completion date based on approved Change Orders 1 through 7 is May 18, 2026.
Due to additional construction time, CMA’s previously authorized administration and inspection budget has been exhausted since April 27, 2026. However, at staff’s request, CMA continued to provide construction engineering services, including administrative services and inspections, necessary to maintain construction oversight and avoid disruption to the project. Based on the latest project schedule provided by FG Construction, the final completion date is December 17, 2026. Task Order No. 4 allows for the additional services which CMA has already provided between April 27, 2026 and September 30, 2026 in the amount of $58,950.50 and will continue to provide through the project closeout in the month of December 2026 for an additional $26,980.00. The total amount for Task Order No. 4 shall not exceed $85,930.50.
RECOMMENDATION: For review and approval
FISCAL IMPACT: $85,930.50 for Task Order No. 4 ($268,506 was previously approved for Task Orders No. 1, 2 & 3). The project is being funded under the approved Margate Boulevard Improvements budget line of the Capital Improvements Program Fund; A/C #340.0510.563056.
CONTACT PERSON: Cale Curtis, CRA Executive Director