TO: Margate CRA Chair and Members of the Board
FROM: Cale Curtis, CRA Executive Director
DATE: November 10, 2026
Title
APPROVING CHANGE ORDER NO. 8 IN THE AMOUNT OF $13,720.00 TO THE MARGATE BOULEVARD CROSSWALK AND LANDSCAPE IMPROVEMENTS PROJECT AGREEMENT WITH FG CONSTRUCTION, LLC. WITH NO ADDITIONAL DAYS FOR COMPLETION; AUTHORIZING THE BOARD CHAIR TO EXECUTE THE CHANGE ORDER
BACKGROUND: In July 2021 the MCRA engaged the services of Chen Moore & Associates, Inc. (CMA) to provide professional civil engineering, planning and landscape architecture services for the design, permitting, and construction administration needed for the Margate Boulevard Crosswalk and Landscape Improvements project.
The project scope includes the sidewalk and crosswalk reconstruction to conform to ADA standards, landscaping improvements including irrigation and energy efficient lighting, improvements of existing stormwater drainage conflict within project limits, and road resurfacing. The project is confined to the right-of-way along Margate Boulevard from US 441 to East River Drive and N.W. 58th Avenue from Park Drive to approximately one half (1/2) block northeast of Margate Boulevard.
In May 2025, the Board approved an agreement with FG Construction LLC in the amount of $1,004,788.71. Construction started on August 14, 2025, with an initial completion date set for April 11, 2026.
The following Change Orders have already been approved by the Board in the amount of $124,483.52 which added an additional 37 days to the completion date:
• On 1/14/26 Change Orders No. 1 & 2 totaling $37,012.49 were approved adding 21 days
• On 2/11/26 Change Orders No. 3, 4 & 5 totaling $86,013.66 were approved adding 14 days
• On 3/11/26 Change Orders No. 6 & 7 totaling $1,457.37 were approved adding 2 days
The extended completion date based on these approved Change Orders is May 18, 2026. The latest project schedule provided by FG Construction indicates final completion date of December 17, 2026.
Change Order No. 8 provides for additional landscaping activities in the amount of $13,720.00 and no additional days. The additional landscaping activities include (1) planting of 455 Flax Lily to replace the removed Coontie Palms at the outer perimeter of the roundabout, (2) planting of four (4) Japanese Blueberry trees replacing the double trunk palm trees at the roundabout, and (3) double trunk palm trees (Christmas Palms) from the roundabout to the existing bus stop on N.W. 58th Avenue.
RECOMMENDATION: For review and approval
FISCAL IMPACT: $13,720.00 for Change Order No. 8. (Change Orders 1 through 7 were previously approved for a total of $124,483.52). This project is being funded under the approved Margate Boulevard Improvements budget line of the Capital Improvements Program Fund; A/C #340.0510.563056.
CONTACT PERSON: Cale Curtis, CRA Executive Director