Legislation Details

File #: ID 2026-332    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 11/20/2026 In control: Regular City Commission Meeting
On agenda: 12/2/2026 Final action:
Title: A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A SOLE-SOURCE PURCHASE, THROUGH EES-FL, FROM SMITH & LOVELESS, INC. OF A 7 MGD PISTA WORKS ALL-IN-ONE SCREENING AND GRIT REMOVAL SYSTEM, WITH A QUOTED PRICE OF $1,459,450 AND A TOTAL PURCHASE AUTHORIZATION NOT TO EXCEED $1,517,895; RECOGNIZING THE MANUFACTURER’S U.S. PRODUCTION AND PROPRIETARY SYSTEM CONFIGURATION; PROVIDING FOR TEMPORARY USE AS BYPASS EQUIPMENT DURING WEST WASTEWATER TREATMENT PLANT HEADWORKS REHABILITATION AND SUBSEQUENT PERMANENT INSTALLATION AT THE EAST WASTEWATER TREATMENT PLANT; AUTHORIZING THE CITY MANAGER TO EXECUTE PURCHASE DOCUMENTS; PROVIDING FOR IMPLEMENTATION; AND PROVIDING FOR AN EFFECTIVE DATE.
Attachments: 1. RESOLUTION, 2. BACKGROUND, 3. BACKGROUND, 4. BACKGROUND, 5. BACKGROUND, 6. BACKGROUND, 7. BACKGROUND, 8. BACKGROUND
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

 

TO:                     Mayor and City Commission

 

FROM:                     Cale Curtis, City Manager

 

DATE:                     December 2, 2026

 

 

Title

A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A SOLE-SOURCE PURCHASE, THROUGH EES-FL, FROM SMITH & LOVELESS, INC. OF A 7 MGD PISTA WORKS ALL-IN-ONE SCREENING AND GRIT REMOVAL SYSTEM, WITH A QUOTED PRICE OF $1,459,450 AND A TOTAL PURCHASE AUTHORIZATION NOT TO EXCEED $1,517,895; RECOGNIZING THE MANUFACTURER’S U.S. PRODUCTION AND PROPRIETARY SYSTEM CONFIGURATION; PROVIDING FOR TEMPORARY USE AS BYPASS EQUIPMENT DURING WEST WASTEWATER TREATMENT PLANT HEADWORKS REHABILITATION AND SUBSEQUENT PERMANENT INSTALLATION AT THE EAST WASTEWATER TREATMENT PLANT; AUTHORIZING THE CITY MANAGER TO EXECUTE PURCHASE DOCUMENTS; PROVIDING FOR IMPLEMENTATION; AND PROVIDING FOR AN EFFECTIVE DATE.

 

Body

 

 

BACKGROUND:

On December 10, 2025, the City Commission adopted Resolution No. 25-088, awarding RFQ No. 2025-008, Design-Build Wastewater Treatment Plant Headworks Rehabilitation, to Globaltech, Inc., and approving the negotiated Guaranteed Maximum Price agreement for the project in an amount not to exceed $12,909,057, inclusive of contingency allowances.

 

At the time Resolution 25-088 was presented to Commission for consideration, the Headworks Rehabilitation Project was envisioned without the need for a bypass or temporary grit removal system.  However, we have recently converted our former RBC (Rotational Biological Contactor) structure to an aeration basin and we are seeing very positive results in our treatment.  Consequently, it is now critical to remove the grit ahead of the new aeration treatment process to avoid clogging the new air diffusers, contaminating the aeration basin, or degrading our treatment.  So, this resolution will allow wastewater flow to be temporarily bypassed around the existing headworks so that the structure can be taken out of service, allowing the rehabilitation to proceed while wastewater treatment operations continue.

 

Globaltech has provided a proposal to furnish and install a semi-bypass system using rented screening equipment and Conex containers, together with the City’s existing grit classifier. It is designed to treat up to 10 MGD, but Globaltech does not guarantee a specific grit-removal efficiency.

 

The estimated change-order cost is $2,704,532.98 for a 12-month rental period, including approximately $431,000 in fuel. The City would be responsible for day-to-day operation, and additional rental time could increase costs. DEES is evaluating a direct purchase as an alternative that would provide the City with equipment for temporary bypass use at West Plant and planned permanent installation at East Plant.

 

 

The proposed change order assumed a 12-month rental period, included approximately $431,000 for fuel, and relied primarily on rented equipment that the City would not retain as a permanent asset. DEES administration has balked at this proposal and is seeking a more cost-effective avenue to bypass the Headworks structure and remove grit ahead of the aeration treatment.

 

The Smith & Loveless proposal offers a complete headworks system with a fine screen manual bypass bar screen, grit chamber, grit pump, screw conveyor and concentrator, PLC-based (Programmable Logic Controller) controls, and an aluminum skid frame. The quoted equipment price is $1,184,450 with a $275,000 allowance for anticipated design changes during submittal review, for a total quoted amount of $1,459,450, not including any freight charges or any fuel surcharges.

 

The City intends to use the equipment first as temporary bypass of the headworks facility in the West Wastewater Treatment Plant during rehabilitation of the headworks facility and, after that project is complete, to relocate and permanently install the equipment at the smaller East Wastewater Treatment Plant, whose existing headworks equipment is 40 years old, has exceeded its useful life, is in need of replacement, and is currently lacking any grit removal system.

 

The Smith & Loveless quoted equipment and design allowance is almost $1.25MM less than Globaltech’s proposed change-order cost for a similar system before any fuel surcharge, unloading, and installation costs. Unlike Globaltech’s primarily rental-based proposal, the proposed option has the added benefit of being able to be relocated and permanently installed in the East Wastewater Treatment Plant to replace outdated equipment. Reusing the equipment would make the purchase a more cost-effective long-term option for the City.

 

Smith & Loveless, Inc. offers the PISTA Works all-in-one screening and grit removal system, a custom-engineered, integrated package combining screening, a grit chamber, grit pumping and washing equipment, and PLC-based controls. Smith & Loveless identifies the PISTA Works as its proprietary integrated system while the vortex grit chamber geometry is proprietary to Smith & Loveless, Inc. The PISTA Works Model 7.0B with a peak system flow capacity of 7.0 million gallons per day (MGD), will meet the City’s temporary bypass needs at the West Plant as well as the needs of a future permanent installation at the East Plant.

 

Smith & Loveless reports that all of its pumping, headworks, and treatment systems are manufactured at its U.S. facilities in Lenexa, Kansas, and Norwalk, California, using American-produced goods and raw materials.

 

The City Commission finds that purchasing the equipment for temporary use at the West Plant and subsequent permanent use at the East Plant will address the immediate bypass need, will provide equipment for the East Plant, and is in the best interests of the City and its residents.

 

 

RECOMMENDATION:                     Approve the sole-source purchase of one Smith & Loveless Model 7.0B PISTA Works

 

 

FISCAL IMPACT:                     $1,184,450 for equipment plus

$   275,000 allowance for design changes, plus

$   118,445 (10%) allowance for shipping and fuel surcharges.

Total purchase not to exceed $1,517,895

Bond: 464.9090.565001, Project 6054 “Headworks”

 

CONTACT PERSON:                     Curt Keyser, DEES