Skip to main content
File #: ID 2025-067    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 3/6/2025 In control: Community Redevelopment Agency
On agenda: 3/12/2025 Final action:
Title: AUTHORIZING THE WAIVER OF BIDDING REQUIREMENTS; APPROVING THE AWARD OF THE CONTRACTS FOR THE REPLACEMENT OF THE FENCING FABRIC TO CAIBAI CONSTRUCTION, INC., AND THE RESURFACING OF THE BASKETBALL AND TENNIS COURTS TO FAST DRY COURTS, INC., AS PART OF THE CORAL GATE PARK IMPROVEMENTS PROJECT
Attachments: 1. RESOLUTION, 2. BACKGROUND: CAIBAI PROPOSAL, 3. BACKGROUND: TROPIC PROPOSAL, 4. BACKGROUND: FDC PROPOSAL, 5. BACKGROUND: SPORT SURFACES QUOTE 1, 6. BACKGROUND: SPORT SURFACES QUOTE 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

TO: Margate CRA Chair and Members of the Board

FROM: Cale Curtis, CRA Executive Director

DATE: March 12, 2025


Title
AUTHORIZING THE WAIVER OF BIDDING REQUIREMENTS; APPROVING THE AWARD OF THE CONTRACTS FOR THE REPLACEMENT OF THE FENCING FABRIC TO CAIBAI CONSTRUCTION, INC., AND THE RESURFACING OF THE BASKETBALL AND TENNIS COURTS TO FAST DRY COURTS, INC., AS PART OF THE CORAL GATE PARK IMPROVEMENTS PROJECT

Body


BACKGROUND: The MCRA is undertaking several improvements at Coral Gate Park in accordance with the FY 2025 budget. In an effort to save time and cost, the MCRA has entered into a series of contracts, usually based on CO-OP or "piggyback" contracts with specialized vendors instead of using a single general contractor with subcontractors to perform the work. To date, repaving the walking paths, replacement of benches, installation of new sports lighting, and sod replacement have been authorized using this approach.

A proposal for replacement of dated old fence fabric surrounding the sports courts was obtained from Tropic Fence, Inc., based on Tropic's annual contract with the City of Ft. Lauderdale. Although the use of this piggyback contract was initially considered, there were concerns over the quoted cost ($45,540) and certain terms in the Ft. Lauderdale contract that did not precisely match the desired scope of work at Coral Gate Park. A second quote was therefore solicited from Caibai Construction, a firm that had satisfactorily performed fencing installation for DEES. Caibai's quote of $36,000 represented a savings of over 20% compared to Tropic Fence. Although the total cost slightly exceeds the limit exempted from formal bidding, staff have concluded that bidding this fencing project is unlikely to result in further savings and would cause an unnecessary delay in completing the work. Awarding the fencing contract to Caibai Construction is thus recommended.

A proposal was received from Fast-Dry Courts, Inc. (FDC) in the amount of $35,...