Legislation Details

File #: ID 2026-080    Version: 1 Name:
Type: Consent - Resolution Status: Agenda Ready
File created: 3/25/2026 In control: Regular City Commission Meeting
On agenda: 4/15/2026 Final action:
Title: A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A PROPOSAL FROM GIANNETTI CONTRACTING CORPORATION FOR DESIGN-BUILD SERVICES RELATED TO THE SOUTH CREEK SERVICE AREA EAST SIDE WATER MAIN REPLACEMENT PROJECT, PURSUANT TO THE CITY'S CONTINUING SERVICES CONTRACT AND IN ACCORDANCE WITH CCNA; PROVIDING CONSISTENCY WITH THE INTERLOCAL AGREEMENT WITH THE CITY OF COCONUT CREEK; PROVIDING FOR AN EFFECTIVE DATE
Attachments: 1. RESOLUTION, 2. BACKGROUND, 3. BACKGROUND, 4. BACKGROUND, 5. BACKGROUND, 6. BACKGROUND, 7. BACKGROUND, 8. BACKGROUND
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

TO: Mayor and City Commission

FROM: Cale Curtis, City Manager

DATE: April 15, 2026


Title
A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A PROPOSAL FROM GIANNETTI CONTRACTING CORPORATION FOR DESIGN-BUILD SERVICES RELATED TO THE SOUTH CREEK SERVICE AREA EAST SIDE WATER MAIN REPLACEMENT PROJECT, PURSUANT TO THE CITY'S CONTINUING SERVICES CONTRACT AND IN ACCORDANCE WITH CCNA; PROVIDING CONSISTENCY WITH THE INTERLOCAL AGREEMENT WITH THE CITY OF COCONUT CREEK; PROVIDING FOR AN EFFECTIVE DATE

Body


BACKGROUND: The City of Margate, Department of Environmental and Engineering Services (DEES), is implementing a comprehensive water main replacement program across its service areas. Project priorities have been identified through the City's hydraulic model (June 2022), which evaluates infrastructure based on age, material condition, frequency of breaks, fire flow deficiencies, and overall system performance.

The South Coconut Creek service area has been identified as a priority due to aging infrastructure, operational deficiencies, and the need to improve system reliability and fire protection. On June 18, 2025, the City of Margate entered into an Interlocal Agreement with the City of Coconut Creek to coordinate and complete water main replacement improvements within this service area by December 31, 2028.

To advance this effort, the City utilized its design-build continuing services contracts awarded also on June 18, 2025 under Resolution 25-039. In August 2025, the City initiated negotiations with David Mancini & Sons, a qualified contractor with extensive experience in underground utility construction. However, after approximately six (6) months of coordination, the City did not receive a proposal, and negotiations were discontinued due to lack of responsiveness.

The City subsequently engaged Giannetti Contracting Corporation under the same continuing services contract (25-039) and successfully negotiated a proposal to perform the required design-bui...