Title: A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A SOLE-SOURCE PURCHASE, THROUGH EES-FL, FROM SMITH & LOVELESS, INC. OF A 7 MGD PISTA WORKS ALL-IN-ONE SCREENING AND GRIT REMOVAL SYSTEM, WITH A QUOTED PRICE OF $1,459,450 AND A TOTAL PURCHASE AUTHORIZATION NOT TO EXCEED $1,517,895; RECOGNIZING THE MANUFACTURER’S U.S. PRODUCTION AND PROPRIETARY SYSTEM CONFIGURATION; PROVIDING FOR TEMPORARY USE AS BYPASS EQUIPMENT DURING WEST WASTEWATER TREATMENT PLANT HEADWORKS REHABILITATION AND SUBSEQUENT PERMANENT INSTALLATION AT THE EAST WASTEWATER TREATMENT PLANT; AUTHORIZING THE CITY MANAGER TO EXECUTE PURCHASE DOCUMENTS; PROVIDING FOR IMPLEMENTATION; AND PROVIDING FOR AN EFFECTIVE DATE.
Attachments: 1. RESOLUTION, 2. BACKGROUND, 3. BACKGROUND, 4. BACKGROUND, 5. BACKGROUND, 6. BACKGROUND, 7. BACKGROUND, 8. BACKGROUND
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

TO: Mayor and City Commission

FROM: Cale Curtis, City Manager

DATE: December 2, 2026


Title
A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING A SOLE-SOURCE PURCHASE, THROUGH EES-FL, FROM SMITH & LOVELESS, INC. OF A 7 MGD PISTA WORKS ALL-IN-ONE SCREENING AND GRIT REMOVAL SYSTEM, WITH A QUOTED PRICE OF $1,459,450 AND A TOTAL PURCHASE AUTHORIZATION NOT TO EXCEED $1,517,895; RECOGNIZING THE MANUFACTURER’S U.S. PRODUCTION AND PROPRIETARY SYSTEM CONFIGURATION; PROVIDING FOR TEMPORARY USE AS BYPASS EQUIPMENT DURING WEST WASTEWATER TREATMENT PLANT HEADWORKS REHABILITATION AND SUBSEQUENT PERMANENT INSTALLATION AT THE EAST WASTEWATER TREATMENT PLANT; AUTHORIZING THE CITY MANAGER TO EXECUTE PURCHASE DOCUMENTS; PROVIDING FOR IMPLEMENTATION; AND PROVIDING FOR AN EFFECTIVE DATE.

Body


BACKGROUND:
On December 10, 2025, the City Commission adopted Resolution No. 25-088, awarding RFQ No. 2025-008, Design-Build Wastewater Treatment Plant Headworks Rehabilitation, to Globaltech, Inc., and approving the negotiated Guaranteed Maximum Price agreement for the project in an amount not to exceed $12,909,057, inclusive of contingency allowances.

At the time Resolution 25-088 was presented to Commission for consideration, the Headworks Rehabilitation Project was envisioned without the need for a bypass or temporary grit removal system. However, we have recently converted our former RBC (Rotational Biological Contactor) structure to an aeration basin and we are seeing very positive results in our treatment. Consequently, it is now critical to remove the grit ahead of the new aeration treatment process to avoid clogging the new air diffusers, contaminating the aeration basin, or degrading our treatment. So, this resolution will allow wastewater flow to be temporarily bypassed around the existing headworks so that the structure can be taken out of service, allowing the rehabilitation to proceed while wastewater treatment operations continue.

Globaltech has provided a propos...