File #: ID 2024-350    Version: 1 Name:
Type: Consent - Resolution Status: Agenda Ready
File created: 10/11/2024 In control: Regular City Commission Meeting
On agenda: 11/6/2024 Final action:
Title: A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING THE WAIVER OF BIDDING REQUIREMENTS FOR THE COMPLETE REPAIR OF THE EAST ACCELATOR TANK USED IN THE WATER TREATMENT PROCESS, AND AWARDING THE CONTRACT TO TITANS PROTECTIVE COATINGS, LLC, FOR LABOR AND MATERIALS AT A COST OF $671,535.00 PLUS FIVE PERCENT CONTINGENCY; PROVIDING FOR TIMELY AND COST EFFECTIVE REPAIRS
Attachments: 1. RESOLUTION, 2. BACKGROUND, 3. BACKGROUND, 4. PHOTO, 5. PHOTO, 6. PHOTO
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

TO: Mayor and City Commission

FROM: Cale Curtis, City Manager

DATE: November 6, 2024


Title
A RESOLUTION OF THE CITY OF MARGATE, FLORIDA, APPROVING THE WAIVER OF BIDDING REQUIREMENTS FOR THE COMPLETE REPAIR OF THE EAST ACCELATOR TANK USED IN THE WATER TREATMENT PROCESS, AND AWARDING THE CONTRACT TO TITANS PROTECTIVE COATINGS, LLC, FOR LABOR AND MATERIALS AT A COST OF $671,535.00 PLUS FIVE PERCENT CONTINGENCY; PROVIDING FOR TIMELY AND COST EFFECTIVE REPAIRS

Body


BACKGROUND: DEES Utilities Division is committed to the upkeep of the City's utility facilities, including the operation and maintenance of the City's water treatment plant, which requires the continuous maintenance and repair of its treatment units to ensure operational continuity and water quality.

The water treatment plant has redundancy with two accelator tanks that operate on a rotational basis, both of which have experienced compromised structural integrity since they were first put into operation.

The west accelator tank was rehabilitated two years ago with the application of industry-approved coatings. In the course of that project we blasted the exterior stucco off the tank and found over 70 leaks in the tank (See photos attached). We consulted with structural experts, coating experts, and industry leaders to develop and implement a practical and effective approach to address the structural issues with the tank. In the end, we brought in Titans Protective Coatings, LLC to implement the chosen approach and to complete that project. The approach we implemented has resulted in significant improvement in the tank's integrity.

The east accelator tank is now in need of similar rehabilitation and repairs in order to allow the transfer of operations from the west tank, required for routine maintenance. Both the west and east tank were originally constructed at the same time by the same contractor, and the east tank is exhibiting similar symptoms as the west tank was prior to its reha...