TO: Mayor and City Commission
FROM: Cale Curtis, City Manager
DATE: July 5, 2023
Title
AUTHORIZING EXPENDITURES FOR BOND RELATED PROJECTS AT SOUTHEAST TO INCLUDE CONVERSION OF TWO (2) ARTIFICIAL TURF SOCCER FIELDS, UTILIZING ESTABLISHED GOVERNMENTAL CONTRACT PRICING; SHALL NOT EXCEED $2,444,355
BACKGROUND: During a March 14, 2023 City Commission meeting there was a workshop item to discuss the status of projects utilizing Park Bond Capital Improvement funds, and to consider the reprioritization of all or part of certain remaining projects by the City Commission. One of the projects discussed was the conversations of two (2) artificial turf soccer fields. This improvement includes a turnkey installation of two (2) Field Turf, Inc artificial turf soccer fields by a certified field builder at a cost of $2,394,355, with the remaining funds for contingency of other site upgrades.
RECOMMENDATION: TO APPROVE
FISCAL IMPACT: $2,444,355 Accounts 335-6501-572.65-81
CONTACT PERSON: Michael A. Jones, CPRP-Director of Parks and Recreation