TO: Mayor and City Commission
FROM: Cale Curtis, City Manager
DATE: June 18, 2025
Title
RESOLUTION - APPROVING AMENDMENT TO CONSTRUCTION CONTRACT, BID NO. 2020-014 - MARGATE FIRE STATION 58 - DEMOLITION AND CONSTRUCTION, WITH SISCA CONSTRUCTION SERVICES, LLC.; PROVIDING FOR FULL AND FINAL COMPENSATION; PROVIDING FOR AN EFFECTIVE DATE.
BACKGROUND: The City entered into a construction contract, Bid No. 2020-014 Margate Fire Station No. 58 - Demolition and Construction (the "Contract"), with Sisca Construction Services, LLC, which was approved by the City on November 4, 2020, by Resolution No. 20-091. Disputes have arisen between the Parties concerning the performance of the Contract. This Contract Amendment resolves all outstanding disputes.
RECOMMENDATION: For approval.
FISCAL IMPACT: $111,250
CONTACT PERSON: Cale Curtis, City Manager